Understanding the URS Corporation v BDW Trading Supreme Court Ruling on Building Safety Act 2025
The construction industry received definitive guidance on the Building Safety Act 2022's practical application when the Supreme Court delivered its landmark judgment in URS Corporation Ltd v BDW Trading Ltd [2025] UKSC 21 on May 21, 2025. This unanimous decision by a full seven-justice panel doesn't merely resolve a dispute between two parties—it establishes fundamental principles governing construction liability for decades to come, particularly regarding historic building defects, the responsibility for remedial works, and the retrospective application of extended limitation periods affecting projects completed as far back as 1992.
This 88-page judgment represents the first time the Supreme Court has considered claims arising under the Building Safety Act 2022, making it essential reading for developers, design consultants, main contractors, professional indemnity insurers, and legal professionals navigating the post-Grenfell regulatory landscape. The Court addressed four critical questions about voluntary repairs, retrospective legislation, developer rights under the Defective Premises Act 1972, and contribution claims without formal proceedings—each answer reshaping how construction professionals approach risk, liability, and remedial obligations across England and Wales.
At the heart of this dispute lay a scenario increasingly familiar in post-Grenfell Britain: serious structural defects discovered in high-rise residential buildings years after completion. BDW Trading, the original developer, had engaged URS Corporation as structural design consultant for the Capital East and Freemens Meadow developments completed between 2007 and 2012. When post-Grenfell safety investigations in late 2019 revealed potentially dangerous design defects affecting structural integrity, BDW faced a critical decision that would test the boundaries of construction law and establish precedents affecting billions of pounds in potential liability across the UK construction sector.
Table Of Contents
- • URS v BDW Case Summary: Quick Reference
- • Four Grounds of Appeal: Detailed Analysis
- • Building Safety Act 30-Year Liability Extension Explained
- • Design Defect Liability for Developers and Consultants
- • Who's Affected: Stakeholder Impact Analysis
- • Practical Risk Management Strategies
- • When to Seek Building Safety Act Legal Advice
- • Frequently Asked Questions
URS v BDW Case Summary: Quick Reference
The URS Corporation Ltd v BDW Trading Ltd [2025] UKSC 21 case involved a dispute between URS Corporation (structural design consultant) and BDW Trading (property developer) over liability for remedial works on high-rise residential developments with structural defects discovered years after completion. The case reached the Supreme Court after lower courts consistently ruled in favor of BDW's right to recover costs for voluntary safety repairs undertaken on buildings it no longer owned, with the Building Safety Act 2022's retrospective limitation period extension adding critical complexity to already intricate construction liability questions.
Case Element | Details |
---|---|
Case Name | URS Corporation Ltd (Appellant) v BDW Trading Ltd (Respondent) |
Citation | [2025] UKSC 21 |
Court | Supreme Court of the United Kingdom (Full Seven-Justice Panel) |
Justices | Lords Hamblen, Burrows, Leggatt, Lloyd-Jones, Briggs, Sales, and Richards |
Judgment Date | 21 May 2025 |
Outcome | Unanimous dismissal of URS appeal on all four grounds |
Judgment Length | 88 pages (comprehensive legal analysis) |
Historic Significance | First Supreme Court case interpreting Building Safety Act 2022 |
Key Legislation | Building Safety Act 2022, Defective Premises Act 1972, Civil Liability (Contribution) Act 1978 |
Limitation Period Change | Extended from 6 years to 30 years (retrospective from 28 June 2022) |
Projects Affected | Capital East and Freemens Meadow (high-rise residential, completed 2007-2012) |
Defects Discovered | Late 2019 (post-Grenfell safety investigations) |
Original Claim Filed | 6 March 2020 (pre-Building Safety Act) |
BSA Section 135 Effective Date | 28 June 2022 |
Government Intervention | Secretary of State intervened on Ground 2 (represented by Michael Walsh KC and Jason Pobjoy KC) |
Timeline of the URS v BDW Case
- 2007-2012: Capital East and Freemens Meadow developments completed by BDW with URS structural design services
- Late 2019: Post-Grenfell safety investigations reveal serious structural defects affecting building integrity
- 2020-2021: BDW voluntarily undertakes comprehensive remedial works despite no longer owning the properties
- 6 March 2020: BDW files negligence claim against URS (pre-Building Safety Act, initially time-barred under DPA)
- 28 April 2022: Building Safety Act 2022 receives Royal Assent
- 28 June 2022: Section 135 BSA comes into force, extending limitation periods retrospectively to 30 years
- October 2022: BDW successfully amends claim to include DPA and Contribution Act claims (Adrian Williamson KC judgment)
- 3 July 2023: Court of Appeal dismisses URS appeals (Coulson LJ leading judgment)
- 21 May 2025: Supreme Court unanimously dismisses URS appeal on all four grounds with 88-page judgment
Four Grounds of Appeal: Detailed Analysis
The Supreme Court's examination of URS Corporation's four grounds of appeal provides comprehensive guidance on critical construction law questions that will influence disputes for decades to come. Each ground received detailed consideration, with Lord Hamblen and Lord Burrows delivering the leading joint judgment on Grounds 1-3, while Lord Leggatt provided the lead judgment on Ground 4, with all seven justices reaching unanimous conclusions rejecting URS's arguments and affirming developer rights to recover costs for responsible remediation efforts.
Ground | URS Argument | Supreme Court Decision | Industry Impact |
---|---|---|---|
Ground 1: Voluntary Repairs | Losses irrecoverable as "voluntarily incurred" without enforceable legal obligation and in respect of property with no proprietary interest, falling outside duty of care scope and/or too remote | UNANIMOUSLY REJECTED - No "voluntariness principle" exists in law to bar recovery; repairs addressing death/injury risks arguably not voluntary in meaningful sense | Developers can recover costs for responsible safety repairs; construction professionals cannot escape liability simply because remedial works undertaken voluntarily by responsible building owners |
Ground 2: BSA Limitation Extension | Section 135 retrospective extension applies only to direct claims under section 1 DPA, not to related negligence or contribution claims | UNANIMOUSLY REJECTED - Section 135 covers any action "by virtue of" DPA regardless of specific legal mechanism employed; broad interpretation aligns with BSA protective purpose | Extended 30-year limitation period applies comprehensively to negligence claims, contribution claims, and all related legal actions connected to DPA duties; projects back to 1992 now exposed |
Ground 3: Developer Rights Under DPA | DPA section 1(1)(a) applies exclusively to property owners and occupiers, not to commercial developers ordering construction work | UNANIMOUSLY REJECTED - Act imposes duties to "any person" including developers to whose order dwellings are constructed; no contradiction in developers simultaneously owing and being owed duties under DPA | Developers protected when ordering construction work; consultants and contractors owe clear duties to developer clients under DPA; complex web of relationships in modern construction fully recognized |
Ground 4: Contribution Without Judgment | Contribution claims premature without prior judgment, admission of liability, or settlement between claimant and homeowners; no homeowner claim ever asserted against BDW | UNANIMOUSLY REJECTED - "Payment in kind" through remedial works constitutes sufficient basis; contribution right arises when (i) damage suffered for which both parties liable and (ii) one party has paid/ordered/agreed to pay compensation | Developers can carry out remedial works and immediately claim contribution from liable consultants/contractors even without homeowner lawsuits, judgments, or settlements; eliminates waiting for formal proceedings |
Ground 1: Voluntary Repairs and the "Voluntariness Principle"
URS's primary argument centered on characterizing BDW's repair works as "voluntary" because BDW had no proprietary interest in the buildings when repairs were undertaken and faced no enforceable legal obligation to perform the works. URS contended that voluntarily incurred losses fall outside a consultant's duty of care scope and/or are too remote for recovery under standard negligence principles, attempting to establish a "voluntariness principle" that would limit professional liability to scenarios involving legal compulsion or property ownership requirements.
The Supreme Court firmly rejected this position, establishing that voluntarily incurred losses can indeed be recoverable when they fall within the scope of an assumption of responsibility relationship. More significantly, the Court questioned whether repairs addressing risks of death or serious injury to residents could genuinely be considered "voluntary" in any meaningful sense, recognizing the moral and practical imperatives driving responsible developers to address safety risks regardless of technical legal obligations or current property ownership status.
Ground 2: Retrospective Application of Section 135 Building Safety Act
Section 135 of the Building Safety Act 2022, which came into force on June 28, 2022, retrospectively extended limitation periods for claims under the Defective Premises Act 1972 from six years to 30 years for work completed before that date. URS argued this extension applied narrowly to direct claims brought specifically under section 1 DPA, not to related negligence claims, contribution claims under the Civil Liability (Contribution) Act 1978, or other connected legal actions that merely reference or depend upon DPA time bars.
The Supreme Court's interpretation proved expansively protective of claimants, ruling that Section 135 covers any action "by virtue of" the Defective Premises Act, regardless of the specific legal mechanism or cause of action employed. This broad interpretation aligns with the Building Safety Act's underlying legislative purpose: ensuring those responsible for building defects face appropriate accountability regardless of when defects are discovered, preventing technical limitation arguments from defeating meritorious claims against negligent construction professionals.
Building Safety Act 30-Year Liability Extension Explained
The Building Safety Act 2022's extension of limitation periods from six years to 30 years for claims under the Defective Premises Act 1972 represents one of the most significant changes to construction professional liability in modern UK legal history. This retrospective extension, covering work completed before June 28, 2022, creates potential exposure for projects dating back to 1992, fundamentally altering the risk landscape for developers, design consultants, main contractors, and their professional indemnity insurers who must now account for three decades of potential liability rather than the traditional six-year window.
Understanding Section 135 of the Building Safety Act
Section 135 operates retrospectively, meaning that claims which were previously time-barred under the old six-year limitation period can be revived if they fall within the new 30-year period. The Supreme Court confirmed that this extended period applies not only to direct claims under section 1 of the Defective Premises Act but also to related negligence claims, contribution claims under the Civil Liability (Contribution) Act 1978, and any other legal action connected to DPA duties, creating comprehensive liability exposure across multiple potential causes of action.
- Work Completed Before June 28, 2022: 30-year limitation period applies retrospectively from completion date (projects back to 1992 now exposed)
- Work Completed After June 28, 2022: 15-year limitation period applies prospectively from completion date
- Revival of Time-Barred Claims: Claims that expired during 12 months before June 28, 2022 can be brought within extended period
- Scope of Application: Covers direct DPA claims, negligence claims, contribution claims, and any action "by virtue of" DPA
- Exception: Claims finally determined or settled before June 28, 2022 cannot be reopened
Who's Affected by the 30-Year Limitation Period
The extended limitation period creates profound implications across the construction industry, affecting parties involved in residential dwelling design, construction, conversion, or enlargement projects completed as far back as 1992. Design consultants including architects, structural engineers, and specialist designers face particularly acute exposure given that design defects often remain undiscovered for many years after construction completion, with problems only manifesting when buildings age or undergo post-Grenfell safety investigations revealing latent structural or fire safety issues.
Main contractors, specialist subcontractors, and materials suppliers also face extended liability periods, though the URS v BDW judgment clarifies that developers who act responsibly to address safety risks can pursue contribution claims throughout the supply chain to recover remediation costs. Professional indemnity insurers must now provide coverage extending 30 years beyond project completion for historic work, requiring fundamental reassessment of risk models, premium structures, and policy terms to account for this dramatically expanded exposure window that quintuples the traditional six-year liability period.
Design Defect Liability for Developers and Consultants
The URS v BDW judgment provides critical clarity on design defect liability affecting both developers who commission construction work and the consultants they engage to provide professional services. The case establishes that design consultants owe clear duties not only to ultimate property owners and occupiers but also to the developers who engage their services, creating a comprehensive duty framework where contractual relationships generate both contractual and statutory obligations under the Defective Premises Act 1972 alongside common law negligence duties.
Professional Negligence Standards in Construction Design
Construction design professionals must exercise reasonable skill and care appropriate to their profession when providing services related to residential dwellings. The Supreme Court confirmed that URS assumed responsibility to BDW under professional service contracts and breached the resulting duty of care by providing defective structural designs that created safety risks requiring expensive remediation years after project completion, establishing clear liability despite the passage of time and BDW's disposal of the affected properties before defects were discovered.
Design defect liability extends beyond obvious structural failures to encompass fire safety issues, building envelope defects, inadequate waterproofing, thermal bridging problems, and other latent defects that may not manifest for years after completion. The post-Grenfell regulatory environment has heightened scrutiny of historic design decisions, with many developers conducting retrospective safety investigations that reveal defects in projects previously considered satisfactory, creating waves of potential claims against design professionals who worked on buildings completed years or decades ago.
Common Design Defects Leading to Liability Claims
- Structural Inadequacies: Undersized beams, insufficient reinforcement, inadequate load-bearing capacity affecting building safety
- Fire Safety Design Failures: Inadequate compartmentation, deficient escape routes, non-compliant fire suppression systems
- External Wall System Defects: Combustible materials, inadequate cavity barriers, non-compliant cladding specifications
- Building Envelope Failures: Inadequate waterproofing, thermal bridging, condensation risk, weatherproofing deficiencies
- Services Design Errors: Undersized drainage, inadequate ventilation, non-compliant electrical/mechanical systems
- Accessibility Compliance Failures: Non-compliant disabled access, inadequate emergency egress for mobility-impaired residents
Developer Rights to Pursue Design Consultants
Ground 3 of the URS appeal specifically addressed whether developers could benefit from Defective Premises Act protections, with URS contending the Act's provisions applied exclusively to property owners and occupiers rather than commercial developers. The Supreme Court demolished this argument, confirming that section 1(1)(a) DPA imposes duties to "any person" — explicitly including developers — to whose order dwellings are constructed, establishing clear statutory protection for developers alongside their contractual remedies against negligent consultants and contractors.
Importantly, the Court recognized no contradiction in developers simultaneously owing duties to homeowners while being owed duties by consultants and contractors, acknowledging the complex web of relationships characterizing modern construction projects. This recognition validates contribution claim strategies where developers who discharge remediation obligations to protect residents can immediately pursue recovery throughout the supply chain, identifying all parties whose negligence contributed to the defects requiring repair work and allocating liability according to relative culpability and contractual risk allocation.
Who's Affected: Stakeholder Impact Analysis
The Supreme Court's URS Corporation v BDW Trading decision reverberates far beyond the immediate parties, establishing principles reshaping risk management, insurance, and commercial litigation strategies across the construction sector. Understanding stakeholder-specific implications proves essential for construction professionals, developers, insurers, and legal advisors navigating the post-judgment landscape where accountability extends decades beyond project completion and traditional liability defenses face significant judicial skepticism.
Stakeholder | Impact of URS v BDW Judgment | Immediate Action Required | Risk Level |
---|---|---|---|
Property Developers | Can recover costs for responsible remedial works undertaken to address safety risks; protected under DPA when ordering construction; can pursue contribution throughout supply chain even without homeowner litigation | Document all safety-related expenditure comprehensively; pursue contribution claims against consultants/contractors; conduct portfolio reviews identifying potential defect issues requiring proactive remediation | POSITIVE IMPACT |
Design Consultants (Architects, Engineers) | 30-year liability exposure for historic projects back to 1992; voluntary repairs defense rejected; extended period applies to negligence claims not just DPA; "voluntariness principle" argument failed | Review professional indemnity insurance for 30-year coverage; implement 30-year document retention policies; conduct risk assessment of historic project portfolio (1992-2022); review run-off insurance arrangements | VERY HIGH RISK |
Main Contractors | Extended liability periods create increased contribution claim exposure; developers can pursue recovery throughout supply chain; payment in kind through repairs sufficient for contribution claims | Review subcontractor agreements for back-to-back provisions; ensure subcontractors maintain adequate insurance; implement comprehensive document retention policies; assess historic project risks | HIGH RISK |
Professional Indemnity Insurers | Dramatic increase in claims volume and severity expected; extended 30-year coverage periods required; policies written 1992-2022 now face revived claims; run-off coverage crucial for retired professionals | Reassess risk models and actuarial assumptions; revise policy terms and exclusions; adjust premium structures; establish reserves for historic claims; review run-off provision adequacy | VERY HIGH RISK |
Building Owners/Leaseholders | Protected from remediation cost burden under Building Safety Act; developers and responsible parties must pursue supply chain rather than passing costs to residents; safety-first approach encouraged | Ensure landlords comply with Building Safety Act leaseholder protections; report safety concerns promptly; verify developer pursuing appropriate remediation; understand limitation period protections | PROTECTED (POSITIVE) |
Construction Law Firms | Anticipated surge in Building Safety Act claims, contribution proceedings, and professional negligence litigation; complex multi-party disputes requiring specialized expertise; insurance coverage disputes expected | Develop Building Safety Act and URS v BDW expertise; offer specialized construction defect services; advise clients on document retention and risk management; prepare for increased litigation volume | OPPORTUNITY (POSITIVE) |
Specialist Subcontractors | Extended liability for specialist work (cladding, fire safety systems, structural elements); contribution claims can cascade throughout supply chain; payment in kind creates immediate claim triggers | Verify adequate professional indemnity coverage; review historic project quality; maintain comprehensive records; ensure contractual liability caps where possible; assess main contractor solvency | HIGH RISK |
Building Control Bodies | Potential inclusion in multi-party contribution proceedings where approval decisions questioned; scrutiny of historic building control approvals for defective buildings | Review professional indemnity insurance adequacy; maintain comprehensive approval documentation; assess potential exposure from historic decisions; coordinate with legal advisors on limitation defenses | MODERATE RISK |
Practical Risk Management Strategies
The Supreme Court judgment demands immediate reassessment of risk management approaches across the construction sector, with particular emphasis on extended documentation retention, comprehensive insurance coverage review, and proactive defect management systems addressing the 30-year liability horizon now affecting all construction professionals involved with residential dwelling projects. Organizations that adapt quickly to this new reality will be best positioned to manage risks while continuing to deliver successful construction projects in an environment where accountability extends decades beyond traditional completion and handover milestones.
Enhanced Documentation Standards and Retention Policies
With potential liability horizons extending to 30 years, maintaining comprehensive project documentation becomes crucial for defending against future claims and pursuing contribution recovery from supply chain partners. Design rationales, safety considerations, regulatory compliance evidence, decision-making processes, meeting minutes, correspondence with clients and contractors, and quality assurance records must be preserved far longer than previously contemplated under six-year limitation regimes, requiring substantial investment in digital document management systems and long-term archive facilities.
- Design Documentation: Preserve calculations, specifications, drawings, design development records, and approval documentation for 30 years minimum
- Construction Records: Maintain site diaries, inspection reports, material certificates, testing results, and as-built documentation indefinitely
- Correspondence Archives: Retain emails, letters, meeting minutes, and all client/contractor communications relating to design decisions and safety considerations
- Quality Assurance Evidence: Keep comprehensive records demonstrating compliance with professional standards, building regulations, and safety requirements
- Personnel Accessibility: Maintain contact details for key personnel who may be needed for witness testimony decades after project completion
- Digital Systems: Implement secure cloud-based document management ensuring long-term accessibility and protection against data loss or corruption
Professional Indemnity Insurance Review and Run-Off Coverage
Professional indemnity policies require urgent review to ensure adequate coverage for extended liability periods, with particular attention to run-off insurance arrangements that become essential as the potential for claims extends decades beyond project completion. Standard policy terms may not account for the Building Safety Act's implications, potentially leaving significant coverage gaps that expose professionals to uninsured liability when claims arise 20-30 years after work completion, long after active practice insurance policies have expired or firms have closed operations.
Proactive Defect Management and Portfolio Risk Assessment
The judgment encourages proactive approaches to building defect identification and remediation, with organizations that identify and address defects early finding themselves better positioned to pursue recovery from originally responsible parties while demonstrating responsible stewardship to regulators, insurers, and stakeholders. Regular building condition assessments, systematic defect tracking systems, and portfolio-wide risk reviews enable construction professionals to identify potential liability exposures before they escalate into formal claims, allowing strategic remediation planning and early notification to insurers triggering policy coverage before limitation periods expire.
When to Seek Building Safety Act Legal Advice
The complexity of Building Safety Act 2022 obligations, combined with the Supreme Court's expansive interpretation of liability principles in URS v BDW, creates scenarios where specialist legal advice proves essential for protecting interests and achieving optimal outcomes. Construction professionals, developers, and building owners should consult experienced construction lawyers when facing defect notifications, contemplating remediation strategies, receiving contribution demands, or navigating the intricate regulatory and liability landscape created by post-Grenfell building safety reforms.
Critical Scenarios Requiring Legal Guidance
- Defect Discovery in Historic Projects: When safety investigations reveal defects in buildings completed years ago, requiring assessment of liability exposure and strategic response
- Remediation Cost Recovery: Developers undertaking voluntary repairs needing guidance on pursuing contribution claims throughout supply chain following URS v BDW precedent
- Contribution Claim Defense: Construction professionals receiving demands to contribute to remediation costs requiring strategic defense and liability assessment
- Insurance Coverage Disputes: When professional indemnity insurers deny coverage or dispute liability for Building Safety Act related claims
- Multi-Party Liability Allocation: Complex disputes involving developers, contractors, consultants, and building control requiring sophisticated contribution claim strategies
- Regulatory Compliance Queries: Navigating Building Safety Regulator requirements, building control approvals, and remediation planning obligations
- Limitation Period Questions: Assessing whether claims fall within extended 30-year periods or can be defended on limitation grounds
- Settlement Negotiations: Evaluating settlement proposals against litigation risks in light of URS v BDW principles and Building Safety Act exposure
Frequently Asked Questions About URS v BDW and Building Safety Act
What was the URS v BDW Supreme Court case about?
URS Corporation Ltd v BDW Trading Ltd [2025] UKSC 21 involved a dispute between URS Corporation (structural design consultant) and BDW Trading (property developer) over liability for remedial works on high-rise residential developments with structural defects discovered years after completion. BDW voluntarily undertook expensive safety repairs on the Capital East and Freemens Meadow developments and sought contribution from URS. The Supreme Court unanimously ruled on May 21, 2025 that URS remained liable despite the voluntary nature of repairs, the retrospective application of Building Safety Act limitation extensions, developer rights under the Defective Premises Act, and contribution claims without homeowner litigation. This 88-page judgment by seven justices represents the first Supreme Court interpretation of the Building Safety Act 2022.
How does the Building Safety Act extend limitation periods to 30 years?
Section 135 of the Building Safety Act 2022 retrospectively extended limitation periods for Defective Premises Act 1972 claims from six years to 30 years for work completed before June 28, 2022. The Supreme Court ruled this extension applies not only to direct DPA claims but also to related negligence claims, contribution claims under the Civil Liability (Contribution) Act 1978, and any action "by virtue of" the DPA. This means construction professionals can face liability for building defects discovered decades after project completion, creating exposure for projects dating back to 1992. Work completed after June 28, 2022 has a 15-year limitation period.
Can developers claim under the Defective Premises Act against consultants?
Yes, the Supreme Court in URS v BDW confirmed that developers can benefit from Defective Premises Act protections. The Act imposes duties on anyone providing construction services to developers, creating a clear legal relationship where developers can seek redress from consultants and contractors for defective work. Section 1(1)(a) DPA applies to "any person" including developers to whose order dwellings are constructed. The Court rejected URS's argument that the Act applied only to property owners and occupiers, recognizing that developers can simultaneously owe duties to homeowners while being owed duties by consultants in the complex web of modern construction relationships.
What are voluntary repairs and why do they matter in construction liability?
Voluntary repairs are remedial works undertaken without legal compulsion by parties acting responsibly to address safety risks. The Supreme Court ruled that such repairs can form the basis for contribution claims, particularly when addressing serious safety risks. URS argued that BDW's losses were irrecoverable because repairs were "voluntary" (undertaken without enforceable legal obligation on property BDW no longer owned). The Court firmly rejected this "voluntariness principle," establishing that construction professionals cannot escape liability simply because remedial works were done voluntarily by responsible building owners. The Court questioned whether repairs addressing death or injury risks can genuinely be considered voluntary in any meaningful sense.
How should construction professionals manage extended liability risks?
Construction professionals should enhance documentation standards maintaining comprehensive project records for 30 years minimum, review professional indemnity insurance coverage ensuring adequate extended period protection including run-off arrangements, implement proactive defect management systems conducting portfolio risk assessments of historic projects, and consider their position within complex liability chains understanding how duties flow through construction teams. The 30-year liability horizon requires fundamental changes to risk management approaches, with document retention policies, insurance arrangements, and quality assurance systems updated to reflect dramatically expanded exposure windows affecting projects completed as far back as 1992.
What is a contribution claim under the Civil Liability (Contribution) Act 1978?
A contribution claim allows a party liable for damage to recover contribution from others who are also liable for the same damage, allocating costs according to relative responsibility. The Supreme Court in URS v BDW ruled that contribution claims arise when damage has occurred for which multiple parties are liable and one party has paid, been ordered to pay, or agreed to pay compensation. Critically, the Court established that "payment in kind" through remedial works constitutes sufficient basis for contribution claims. This means developers can carry out repairs and immediately claim contribution from liable consultants/contractors even without homeowner lawsuits, judgments, or settlements—eliminating the need to wait for formal proceedings before recovering costs from responsible supply chain partners.
Which projects are affected by the 30-year limitation period?
The 30-year limitation period applies retrospectively to residential dwelling projects completed before June 28, 2022, creating potential liability exposure for work dating back to 1992. This affects projects involving the design, construction, conversion, or enlargement of dwellings across England and Wales. Design consultants including architects and engineers, main contractors, specialist subcontractors, and materials suppliers face extended liability for historic projects where defects may only manifest years after completion. Post-Grenfell safety investigations have revealed defects in buildings previously considered satisfactory, creating waves of potential claims against professionals who worked on projects completed decades ago. Projects completed after June 28, 2022 have a 15-year limitation period rather than 30 years.
What does URS v BDW mean for professional indemnity insurance?
Professional indemnity insurers face dramatic increases in potential claims volume and severity with the 30-year extended liability period requiring fundamental reassessment of risk models, premium structures, and policy terms. Policies written for projects completed 1992-2022 now face potential revived claims, with insurers needing to establish reserves for historic exposure. Run-off coverage becomes crucial for professionals retiring or closing practices, as claims can arise decades after active practice ceases. Standard policy terms may not account for Building Safety Act implications, potentially leaving coverage gaps. Construction professionals should urgently review insurance coverage ensuring adequate protection for extended periods, with particular attention to run-off insurance arrangements, policy limits, and exclusions that may not address post-judgment liability landscapes shaped by URS v BDW precedent.
Expert Construction Law & Building Safety Act Legal Support
✓ Building Safety Act Claims
Expert representation for developers, contractors, and consultants facing extended liability under the Building Safety Act 2022 and Defective Premises Act 1972 30-year limitation period. Strategic advice on contractual disputes arising from historic building defects.
✓ Contribution & Recovery Claims
Complex multi-party liability disputes, contribution claims under Civil Liability (Contribution) Act 1978, and supply chain recovery strategies following URS v BDW precedent. Specialized commercial litigation for construction defect cases.
✓ Professional Negligence Defense
Strategic defense for design consultants, engineers, and architects facing design defect liability claims. Comprehensive guidance on professional indemnity insurance coverage, limitation defenses, and risk management for extended liability exposure.
The Supreme Court's URS Corporation Ltd v BDW Trading Ltd [2025] UKSC 21 decision creates significant new liabilities for construction professionals, with 30-year exposure for projects dating back to 1992. The judgment's rejection of voluntariness defenses, broad interpretation of Building Safety Act limitation extensions, confirmation of developer rights under the Defective Premises Act, and validation of contribution claims without formal homeowner proceedings fundamentally reshapes construction liability landscapes affecting billions of pounds in potential claims.
Expert legal guidance proves crucial for managing these expanded risks, whether pursuing contribution claims as a developer who undertook responsible remediation, defending against contribution demands as a consultant or contractor facing historic project claims, navigating professional indemnity insurance coverage disputes, or implementing proactive risk management strategies addressing 30-year liability horizons requiring enhanced documentation retention, comprehensive insurance review, and portfolio-wide defect assessments.
For specialist legal advice on Building Safety Act implications, URS v BDW-related claims, construction defect liability, contribution proceedings, or professional negligence defense, contact Connaught Law's construction law specialists for comprehensive support tailored to your specific circumstances in navigating this landmark Supreme Court decision's far-reaching consequences for the UK construction sector.