Building Safety Act 30-Year Limitation 2026: URS v BDW Explained

In URS Corporation Ltd v BDW Trading Ltd [2025] UKSC 21 the Supreme Court held that a developer which repairs defective buildings voluntarily does not lose its claim against the designer responsible. The court dismissed all four grounds of appeal, confirmed that section 135 of the Building Safety Act applies retrospectively, and put the limitation period for historic defects at 30 years. This note sets out what was decided and what it means for developers and consultants.

 ·  Regulated by the Solicitors Regulation Authority  ·  Legal 500  ·  Lexcel

On This Page

Building Safety Act 30-Year Limitation 2026: Urs V Bdw Explained
Building safety liability

What URS v BDW Decided and Why It Matters

This is the first time the Supreme Court has considered the Building Safety Act 2022, and the judgment answers four questions the construction industry had been litigating since the Act passed: whether voluntary repairs can be recovered, how far section 135 reaches back, whether a developer is owed duties under the Defective Premises Act 1972, and when a contribution claim arises. Every answer went against the consultant.

The dispute itself is a familiar post-Grenfell story. BDW Trading developed the Capital East and Freemens Meadow high-rise schemes, completed between 2007 and 2012, with URS Corporation as structural design consultant. Safety investigations in late 2019 revealed serious design defects — and BDW repaired the buildings at its own cost, despite no longer owning them and despite no homeowner having sued. The question was whether it could recover that cost from the designer.

The holding — what the Supreme Court decided, and why it matters

A unanimous seven-justice court dismissed URS's appeal on all four grounds. Liability for work completed before 28 June 2022 now runs for 30 years — reaching projects back to 1992 — and a developer which repairs defects voluntarily keeps its claim against those responsible for them. For consultants and their insurers, files long treated as closed are open again.

Building Safety Act 2022 Uk Infographic — The 30-Year Retrospective Liability Confirmed By Urs V Bdw [2025] Uksc 21 For Defective And Unsafe Buildings

Case Background and Outcome

URS Corporation (structural design consultant) and BDW Trading (developer) fought over who pays for remedial works to high-rise residential buildings whose structural defects surfaced years after completion. BDW's claim began in negligence in March 2020 — before the Building Safety Act existed — and was amended in October 2022 to add Defective Premises Act and Contribution Act claims once section 135 had retrospectively revived the limitation position.

URS lost at every level: at first instance, in the Court of Appeal before Coulson LJ in July 2023, and finally in the Supreme Court on 21 May 2025.

The Case at a Glance

The parties, dates, issues and outcome in the Supreme Court decision, set out in brief.
Case Element Details
Case Name and Citation URS Corporation Ltd (Appellant) v BDW Trading Ltd (Respondent) [2025] UKSC 21
Court and Panel UK Supreme Court, seven justices — joint lead judgment by Lords Hamblen and Burrows (Grounds 1–3), Lord Leggatt (Ground 4)
Judgment Date 21 May 2025
Outcome Unanimous dismissal of URS's appeal on all four grounds
Key Legislation Building Safety Act 2022 (s.135), Defective Premises Act 1972 (s.1), Civil Liability (Contribution) Act 1978
Limitation Change Confirmed 6 years → 30 years retrospectively for work completed before 28 June 2022; 15 years prospectively after
Projects Concerned Capital East and Freemens Meadow — high-rise residential, completed 2007–2012, defects found late 2019

Timeline of the URS v BDW Case

Timeline — the case from build to judgment
  • 2007–2012: Capital East and Freemens Meadow completed by BDW, with URS as structural designer
  • Late 2019: Post-Grenfell safety investigations reveal serious structural design defects
  • 6 March 2020: BDW sues URS in negligence; repairs follow through 2020–2021 at BDW's own cost
  • 28 June 2022: Section 135 of the Building Safety Act comes into force, extending limitation retrospectively to 30 years
  • October 2022: BDW amends its claim to add Defective Premises Act and Contribution Act claims
  • 3 July 2023: Court of Appeal dismisses URS's appeals
  • 21 May 2025: Supreme Court unanimously dismisses the appeal on all four grounds

The Four Grounds of Appeal

Lords Hamblen and Burrows delivered the joint lead judgment on Grounds 1 to 3, Lord Leggatt on Ground 4, and all seven justices agreed on every point. The table gives the shape of each ground; the sections below give the reasoning that matters in practice.

Grounds and Decisions Compared

Each ground of appeal, how the Supreme Court decided it and what the decision turns on.
Ground URS Argument Supreme Court Decision What It Means
1: Voluntary Repairs Losses irrecoverable because repairs were "voluntary" — no legal obligation, no proprietary interest Rejected — no "voluntariness principle" bars recovery; repairs addressing death or injury risks are hardly voluntary in any meaningful sense A developer that repairs responsibly keeps its claim against those who caused the defect
2: Section 135 Reach The 30-year extension applies only to direct DPA claims, not negligence or contribution claims Rejected — s.135 covers any action "by virtue of" the DPA, whatever the legal mechanism The 30-year period carries related negligence and contribution claims with it; projects back to 1992 exposed
3: Duty Owed to Developers The DPA protects homeowners and occupiers, not commercial developers who order the work Rejected — the s.1(1)(a) duty is owed to whoever orders the dwelling, including a developer Developers hold a direct statutory claim against their designers and contractors
4: Contribution Without Judgment No contribution claim without a judgment, admission or settlement — no homeowner ever sued BDW Rejected — the right arises once damage exists and one party has paid, including "payment in kind" by doing the repairs Doing the remedial works itself triggers the contribution right; no need to wait to be sued

Ground 1: Voluntary Repairs and the "Voluntariness Principle"

URS's central argument was that BDW's losses were self-inflicted: it no longer owned the buildings, no one had sued it, and it repaired them anyway. On that footing the losses were said to fall outside the scope of URS's duty of care, or to be too remote. URS needed the court to recognise a "voluntariness principle" — a rule that voluntarily incurred losses are irrecoverable.

The court found no such principle in law. Losses voluntarily incurred can be recovered where they fall within the scope of the assumed responsibility — and the justices doubted the repairs were voluntary in any real sense at all. A developer facing a risk of death or serious injury to residents, with its own name on the buildings, is not exercising free choice in the way the label suggests.

Bottom line — voluntary repairs still carry a claim

A construction professional cannot escape liability because the remedial works were done by someone acting responsibly rather than under compulsion. The absence of a homeowner claim, and the absence of ownership, changed nothing: the cost of putting the defect right remained recoverable from the party who caused it.

Ground 2: Retrospective Application of Section 135 Building Safety Act

Section 135 of the Building Safety Act 2022, in force from 28 June 2022, retrospectively extended limitation for claims under the Defective Premises Act 1972 from six years to 30 for work completed before that date. URS argued the extension applied only to claims brought directly under section 1 of the DPA — not to negligence claims or contribution claims that merely depend on the DPA position.

The court read the section the other way: it covers any action "by virtue of" the Defective Premises Act, whatever the pleaded cause of action. That reading follows the Act's purpose — those responsible for building defects should answer for them whenever the defects come to light — and it stops limitation technicalities defeating claims the Act was passed to enable.

Ground 3: Is a Developer Owed a Duty Under the Defective Premises Act?

URS argued that section 1 of the Defective Premises Act protects buyers of homes, not the developer who commissioned them. The Supreme Court rejected that reading. Section 1(1)(a) is owed to the person who orders the dwelling, and BDW ordered these buildings, so the duty was owed to BDW as well as to the eventual homeowners.

The court saw no inconsistency in a developer being owed a duty while also owing one. Developers are not, as it put it, uniquely privileged — BDW carried the same exposure to its own purchasers throughout. The practical result is that a developer now has a direct statutory claim against its designers and contractors, carrying the Defective Premises Act limitation period rather than the shorter contractual one.

Ground 4: Contribution Without a Judgment or Settlement

The last ground asked when the right to claim contribution under the Civil Liability (Contribution) Act 1978 actually arises. URS said it needed a judgment against BDW, or at least a settlement. The court disagreed: the right arises once damage has been suffered for which both parties are liable and the claimant has paid, agreed to pay, or been ordered to pay compensation for it.

Critically, payment includes payment in kind. Carrying out the remedial work yourself counts, provided the work can be valued in money. BDW had therefore already triggered its contribution right by doing the repairs, without any homeowner ever suing it. The two-year contribution clock runs from the point the amount is fixed, not from the original construction.

The 30-Year Limitation Period Explained

Section 135 rewrote limitation for Defective Premises Act claims: 30 years, retrospectively, for work completed before 28 June 2022, and 15 years prospectively for work completed after. The retrospective limb reaches every residential project completed since 1992 — and after URS v BDW, it carries related negligence and contribution claims with it, not just direct DPA claims.

Understanding Section 135 of the Building Safety Act

The section operates by treating the 30-year period as having always applied, which revives claims that had expired under the old six-year rule. The one hard boundary the Act draws: claims finally determined by a court, or settled, before 28 June 2022 stay closed — everything else within the window is open.

Key points — how Section 135 extends the limitation period
  • Work completed before 28 June 2022: 30-year limitation period, applied retrospectively — completions back to 1992 are in scope
  • Work completed after 28 June 2022: 15-year limitation period, applied prospectively
  • Scope: any action "by virtue of" the DPA — direct claims, related negligence claims and contribution claims alike
  • The exception: claims finally determined or settled before 28 June 2022 cannot be reopened

Who's Affected by the 30-Year Limitation Period

Anyone involved in the design, construction, conversion or enlargement of dwellings completed since 1992. Design consultants — architects, structural engineers, specialist designers — carry the sharpest exposure, because design defects stay latent longest and tend to surface only when a building ages or a safety investigation goes looking. The same extension that exposes consultants also arms building owners: freeholders and leaseholders weighing their position after the Leasehold and Freehold Reform Act 2024 now have three decades of claim to work with, not six years.

Contractors, subcontractors and suppliers face the same window, and professional indemnity insurers now underwrite a 30-year tail on historic work — five times the exposure their pricing models were built on. Where a building insurance claim is also in play, the interaction needs handling together: our note on the Trocadero building insurance litigation covers the insurance side of the same post-Grenfell picture.

Design Defect Liability for Developers and Consultants

What the Ruling Changes for Design Consultants

Three of the four holdings bear directly on consultants. A designer can be pursued under the Defective Premises Act by the developer, not only by homeowners. Section 135 pulls historic work into a 30-year window. And a contribution claim can be brought once the developer has done the repairs, without waiting for anyone to sue.

Taken together, these remove the assumptions a consultant could previously rely on: that limitation had run, that no claimant had emerged, and that a developer fixing its own building was volunteering. None of those now ends the exposure.

Which Design Defects Are Caught

The case concerned structural design of high-rise residential blocks, but nothing in the reasoning confines it to structure or to tall buildings. The Defective Premises Act duty is to see that a dwelling is fit for habitation when completed, so any design failing that standard — fire compartmentation, external wall build-ups, load-bearing calculations, drainage causing damp — falls within the same analysis. Where the argument turns on what competent design required at the time, building surveying standards are usually where the expert evidence starts.

What matters is whether the dwelling was unfit on completion, not whether the defect has yet caused harm. A latent defect that has injured nobody still founds a claim.

The ruling matters most to the consultant who produced the design. BDW had already paid for remedial work when it sued URS, and the court held that a developer which repairs voluntarily does not lose its claim against the designer who caused the defect.

Frequently asked

Questions about URS v BDW and the Building Safety Act

What did the Supreme Court decide in URS v BDW?

URS appealed on four grounds and lost on all of them. The court held that a developer which repairs defects voluntarily can still sue the designer responsible, that section 135 of the Building Safety Act applies retrospectively, that the Defective Premises Act duty is owed to the developer who ordered the dwellings, and that a contribution claim does not need a judgment or settlement behind it. Judgment was given on 21 May 2025.

Does the ruling apply to work carried out before the Building Safety Act?

Yes. That was the point of Ground 2. Section 135 extends the limitation period for Defective Premises Act claims to 30 years for work completed before the Act came into force, and the Supreme Court read that extension broadly enough to carry related negligence and contribution claims with it. Design work from the 1990s and 2000s can still be actionable.

What does "payment in kind" mean for a contribution claim?

It means you do not have to hand over money to start the contribution clock. Carrying out the remedial works yourself counts as payment, provided the work can be valued in money terms. BDW had already done the repairs, and that was enough to give it a contribution right against URS. The two-year period runs from when the amount is fixed.

Can a developer be owed a duty under the Defective Premises Act?

Yes. Section 1(1)(a) is owed to whoever orders the dwelling, which includes the developer, not only the person who later buys it. URS argued a developer needed no such protection; the court disagreed, noting that the developer carries the same exposure to its own purchasers. A developer therefore has a direct statutory claim against its consultants.

What does URS v BDW mean for professional indemnity cover?

It lengthens the tail. A consultant can now face a Defective Premises Act claim from a developer on a project completed decades ago, and a contribution claim brought without any homeowner having sued. That is a question about run-off cover and about how historic projects are recorded, and it is worth raising with your broker rather than assuming a closed file is closed.

Facing a building safety claim?

Tell us when the building was completed, what defects have been identified and what remediation has already been paid for. We’ll tell you whether the extended limitation period reaches your position and who can be pursued.

Get Expert Advice

Disclaimer:

The information in this blog is for general information purposes only and does not purport to be comprehensive or to provide legal advice. Whilst every effort is made to ensure the information and law is current as of the date of publication it should be stressed that, due to the passage of time, this does not necessarily reflect the present legal position. Connaught Law and authors accept no responsibility for loss that may arise from accessing or reliance on information contained in this blog. For formal advice on the current law please don't hesitate to contact Connaught Law. Legal advice is only provided pursuant to a written agreement, identified as such, and signed by the client and by or on behalf of Connaught Law.